On November 13, the City of Rockford, Illinois, named Microsoft as the company evaluating land on the city's south side for a data center campus. According to Baxtel, the property along Edson and Friday roads is controlled by Monarch Energy, whose affiliate Monarch Rock Air holds a memorandum of understanding with the Illinois Department of Commerce and Economic Opportunity for a phased campus of up to 1,400 MW. Microsoft is conducting due diligence and has not submitted a proposal or site plans.

On paper, a lot is in place. Monarch controls the land. Its state agreement was signed in June, before Gov. JB Pritzker's July 1 pause on new Data Center Investment Program applications, which honors earlier agreements. City staff say Rockford's six-month data center moratorium, approved August 3, does not cover the site because of a pre-existing annexation agreement.

The power is a different story. Baxtel reports that ComEd canceled its transmission security agreement with Monarch Rock Air in late July, according to a FERC filing, and that Monarch is now in a later ComEd study process. Charles Koontz, Monarch Energy's chief operating officer and co-founder, told the Rock River Current that the company is "continuing to work with ComEd to provide power to our planned industrial site on a revised timeline."

None of that means the project will not move forward. It does show how a site can have land, incentives and a major prospective user lined up while its power path is still changing.

The national numbers point the same way

New data from Cleanview, reported by OPIS, shows U.S. data center construction starts fell to 8.4 GW across 65 buildings in Q3 2026, down 28% from a record 11.7 GW in Q2 and the first quarterly decline since Q1 2025. October rebounded to 4.6 GW, the second-largest month on record, and year-to-date starts of 33.6 GW are already 1.7 times all of 2025. Cleanview cautions that starts are lumpy and one slow quarter may not signal a trend.

Demand is still strong. What separates the projects that start from the ones that wait is increasingly the power path and the approvals around it. For owners, developers and enterprise users evaluating a site or an existing building, that comes down to four questions.

1. Where does the site sit in the utility's process?

A utility study, an application in the queue and a signed agreement are three very different positions. Ask for the current status in writing, the date of the most recent study, and what changed since the last one. If a seller or broker describes power as "available," find out what that word rests on. In Rockford, the site moved from a transmission security agreement back into a later study. That is the kind of change a buyer needs to know about before setting a price or a schedule.

2. What keeps the power commitment in force?

Utility agreements for large loads often carry financial security, deposits and milestone obligations. Know who holds the agreement, what it requires, whether it transfers with the property, and what happens if a milestone slips. These terms belong in technical due diligence alongside the physical inspection, because they can change the value of a site as much as anything in the building.

3. Which approvals does the site already hold, and which still apply?

Rockford's Monarch site sits outside the city's moratorium because of its annexation agreement, and its state incentive agreement predates the July pause. Even so, DCD reports that Microsoft says it intends to meet the city's new data center standards, which the Zoning Board of Appeals took up at a public hearing on November 17. A site's existing entitlements and the community's current expectations are two separate questions. Map both before committing, and plan for the second even when the first is settled.

4. What does the energization date mean for the rest of the schedule?

Everything downstream keys off the day power arrives: equipment delivery, startup, commissioning and the first customer move-in. A revised utility timeline shifts all of it, and long-lead equipment ordered against the old date can sit idle or need storage. Build the schedule backward from a realistic energization date, carry a contingency for utility slippage, and revisit both whenever the utility's position changes.

Where existing buildings fit

These questions apply to greenfield land and existing buildings alike. A building that already has substantial utility service, a nearby substation or a utility relationship in place can answer several of them faster, which is one reason adaptive reuse keeps drawing attention. It still needs the same scrutiny: what the existing service can carry, what an upgrade would take, and when the utility can deliver it. We walk through the building-level checks in Reading a Building as a Data Center.

MDI Access helps owners, developers and enterprise users evaluate sites and buildings, test the power path and schedule behind them, and manage projects through commissioning as an independent, vendor-neutral advisor.

Talk to one of our advisors about your site or building

Sources

← Back to Insights

Talk to an Advisor

Ready to plan your next data center project?

Get in Touch
855.634.3282
info@mdiaccess.com
Services Solutions Our Work Insights About
© 2026 MDI Access. All rights reserved.